Tenant installation and fit-out explained

What the landlord contributes, what you pay for, the typical process and timeline, and how to avoid the common fit-out cost overruns.

Reviewed by Joe Sokolic · Updated

Commercial space is usually let raw or in the last tenant's layout. Turning it into your office is a construction project with a budget, a programme and a landlord contribution.

The landlord contribution

The tenant installation (TI) allowance is a rand-per-m² amount, larger for a longer lease. It covers a standard fit-out; anything above the allowance — better finishes, more meeting rooms, bespoke joinery — is yours. Get the allowance and what it includes in writing in the offer to lease.

What a fit-out involves

Partitioning, ceilings and lighting, HVAC modifications, electrical and data cabling, flooring, a kitchen, glazing, signage, and access control. On a shell unit this runs to several thousand rand per m²; in an existing office being reconfigured, much less.

The process

Space plan → landlord approval of the plan → contractor pricing → council or body-corporate sign-off where needed → build → occupation certificate. Larger or more bespoke fit-outs need a professional team (space planner, and sometimes an architect and QS).

Timeline

Four to six weeks for a simple reconfiguration; eight to twelve for a full shell fit-out; longer if council approval is on the critical path. The lease normally gives you a beneficial-occupation period to build in before rental starts.

Avoiding overruns

Fix the scope before you price it, keep a 10–15% contingency, and confirm what reinstatement you'll owe at the end so it's budgeted from day one.